Difference between practical completion and partial possession
![]() |
The extent to which building works have been completed and whether a client can occupy a building or not is an issue that often arises during a project. There can be pressure to occupy a building, even if the works are not complete, and this can lead to disputes if the differences in the options available are not properly understood.
[edit] Practical completion
The contract administrator certifies practical completion when all the works described in the contract have been carried out. This is when, leaving aside minor items and/or snagging, the works are considered to be complete.
Once the certificate of practical completion has been issued, the client takes possession of the works for occupation. At this point the contractor no longer has exclusive possession of the site, and their obligation to insure the works and their liability for liquidated damages for delay comes to an end. Depending on the type of contract, at this point the contractor usually becomes entitled to half of the retention monies.
Practical completion signifies the beginning of the defects liability period, during which the contractor must make good any defects that become apparent. It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is the period during which the contractor may be recalled to rectify defects which appear following practical completion. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
[edit] Partial possession
The client may wish to take possession of part of a building or site, even if works are ongoing. This can be programmed within the original contract documents it the need can be foreseen through a requirement for sectional completion, but in the absence of such a provision many contracts offer the more open-ended option of partial possession.
The effect of partial possession is that:
- Any part for which partial possession is given is deemed to have achieved practical completion.
- Half of the retention for that part must be released.
- The defects liability period begins for that part.
- Liquidated damages reduce proportionally.
- The client is responsible for that part and should insure it.
The contractor is not obliged to allow partial possession (although permission cannot be unreasonably withheld), and may not wish to if, for example, access routes are difficult to achieve, it would disrupt the works, or it would incur additional costs. There could also be additional difficulties if the occupants of the part that has been possessed disrupt the contractor, which could result in a claim for extension of time and/or loss and expense.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Government consultations for the summer of 2025
A year of Labour, past and present consultations on the environment, the built environment, training and tax.
CMA competitiveness probe of major housing developers
100 million affordable housing contributions committed with further consultation published.
Homes England supports Greencore Homes
42 new build affordable sustainable homes in Oxfordshire.
Zero carbon social housing: unlocking brownfield potential
Seven ZEDpod strategies for brownfield housing success.
CIOB report; a blueprint for SDGs and the built environment
Pairing the Sustainable Development Goals with projects.
Types, tests, standards and fires relating to external cladding
Brief descriptions with an extensive list of fires for review.
Latest Build UK Building Safety Regime explainer published
Key elements in one short, now updated document.
UKGBC launch the UK Climate Resilience Roadmap
First guidance of its kind on direct climate impacts for the built environment and how it can adapt.
CLC Health, Safety and Wellbeing Strategy 2025
Launched by the Minister for Industry to look at fatalities on site, improving mental health and other issues.
One of the most impressive Victorian architects. Book review.
Common Assessment Standard now with building safety
New CAS update now includes mandatory building safety questions.
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Comments
under JCT D&B 2016, if partial possession is agreed and partial possession certificates are issued for all areas of works individually, does one still need to issue a practical completion certificate at the end of the project?