Difference between practical completion and partial possession
|
The extent to which building works have been completed and whether a client can occupy a building or not is an issue that often arises during a project. There can be pressure to occupy a building, even if the works are not complete, and this can lead to disputes if the differences in the options available are not properly understood.
[edit] Practical completion
The contract administrator certifies practical completion when all the works described in the contract have been carried out. This is when, leaving aside minor items and/or snagging, the works are considered to be complete.
Once the certificate of practical completion has been issued, the client takes possession of the works for occupation. At this point the contractor no longer has exclusive possession of the site, and their obligation to insure the works and their liability for liquidated damages for delay comes to an end. Depending on the type of contract, at this point the contractor usually becomes entitled to half of the retention monies.
Practical completion signifies the beginning of the defects liability period, during which the contractor must make good any defects that become apparent. It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is the period during which the contractor may be recalled to rectify defects which appear following practical completion. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued.
[edit] Partial possession
The client may wish to take possession of part of a building or site, even if works are ongoing. This can be programmed within the original contract documents it the need can be foreseen through a requirement for sectional completion, but in the absence of such a provision many contracts offer the more open-ended option of partial possession.
The effect of partial possession is that:
- Any part for which partial possession is given is deemed to have achieved practical completion.
- Half of the retention for that part must be released.
- The defects liability period begins for that part.
- Liquidated damages reduce proportionally.
- The client is responsible for that part and should insure it.
The contractor is not obliged to allow partial possession (although permission cannot be unreasonably withheld), and may not wish to if, for example, access routes are difficult to achieve, it would disrupt the works, or it would incur additional costs. There could also be additional difficulties if the occupants of the part that has been possessed disrupt the contractor, which could result in a claim for extension of time and/or loss and expense.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.






















Comments
under JCT D&B 2016, if partial possession is agreed and partial possession certificates are issued for all areas of works individually, does one still need to issue a practical completion certificate at the end of the project?